Latest Construction Photos

Here are the latest photos of the progress being made on the new athletic facilities at BYU...

Construction continued this week as workers rushed to finish the concrete floors for the weight room and lockerroom area.  Project engineers hope to begin steel work on January 6th, and estimate it taking about five weeks for the skeleton of the three-story building to be finished.  The underground portion of the building houses all of the mechanical and electrical systems for the building.